1. 62km 132kV Chemosit – Kisii line (completed)
  2. 48km 132kV Rabai Galu line (completed)
  3. 77km 132kV Kilimambogo – Thika – Githambo line (completed)
  4. 20km 132kV Thika – Gatundu (Nyaga) line (completed)
  5. 34km 132kV Mumias – Rangala line (completed)
  6. 122km 132kV Kamburu – Meru line (completed)
  7. 234km 132kV Kindaruma – Mwingi – Garissa line (completed)
  8. 33km 132kV Sotik – Bomet line (completed)
  9. 66km 132kV Eldoret – Kitale line (completed)
  10. 44km 132kV Kisii – Awendo line (completed)
  11. 79km 132kV Nanyuki – Nyahururu (Rumuruti) line (completed)
  12. 33km 132kV Ishiara – Kieni line (completed)
  13. 88km 132kV Narok – Bomet line (completed
  14. 107km 132kV Machakos – Konza, Isinya – Namanga line
  15. 96km 132kV Nanyuki – Isiolo – Meru line
  16. 106km 132kV Sondu – Homabay Ndhiwa – Awendo line
  17. 65km 132kV Lessos – Kabarnet line
  18. 68km 132kV Olkaria – Narok line
  19. 153km 132kV Mwingi – Kitui – Wote – Sultan Hamud line
  20. 138km 220kV Turkwel - Ortum line
  21. 50km 132kV Meru – Maua line
  22. 148km 132kV Nyahururu (Rumuruti) – Maralal line
  23. 50km 132kV Awendo – Isebenia line
  24. 240km 220kV Garsen – Hola – Bura – Garissa line
  25. 60km 132kV Galu – Lunga Lunga line
  26. 330km 220kV Garissa – Habaswen – Wajir line
  27. 107km 132kV Voi – Taveta line
  28. 60km 132kV Rabai – Bamburi – Kilifi line
  29. 111km 132kV Kabarnet – Nyahururu (Rumuruti) line
  30. 70km 220kV Kisumu – Kakamega – Musaga line
  31. 73km 132kV Webuye – Kimilili – Kitale line
  32. 48km 132kV Sotik – Kilgoris line
  33. 38km 400kV Isinya – Konza line
  34. 144km 132kV Kitui – Mutomo – Kibwezi line
  35. 84km 132kV Ngong – Magadi line
  36. Establishments of 132/33kV substation at Uplands
  37. 15km 132kV Galu T-off – Likoni line
  38. 41km 132kV Mumias – Myanga – Busia line
  39. 72km 132kV Rangala – Bondo – Ndigwa line
  40. 72km 132kV Homa Bay – Sindo line
  41. 72km 132kV Ndhiwa – Karungu Bay line
  42. 152km 220kV Isiolo – Maralal line
  43. 228km 220kV Turkwel – Lodwar – Lokichogio line
  44. 140km 132kV Rumuruti-Maralal line