Status
Completed
Length
26km
Volt
132kV
Commissioned
September 2015

Financier
KCB Belgium

Contractor
KBC Bank of Belgium

Scope

Construction of a 26km, 132kV line from Meru to Isiolo and substations at Meru and Isiolo

Benefit

Reliable power supply from Nanyuki, which generates hydropower from Masinga dam, to Meru and subsequently to Ishiara, Kamburu, Mang’u and Juja