Status
Ongoing
Length
520km
Volt
400kv

Financier
To be determined through EPC + F

Contractor
Lot A – NARI Group corporation from China.
Lot B – Sinotek / GTSCC Joint venture from China.
Lot C – NARI Group corporation from China.

Scope

Construction of 520km 400kv double circuit line and associated substations.

 

Benefit

Evacuate power from proposed 960MW Lamu coal plant.