Status
Completed
Length
42km
Volt
132kV
Commissioned
June 2019

Financier
African Development Bank (AfDB)

Contractor
Jyoti Structures Limited
China CAMC Engineering Company Limited

Scope

Construction of a 42km 132kV transmission line, new 132/33kV new substations at Sultan Hamud and Wote

Benefit

Increase electricity access within Makueni County and surrounding areas