Status
Completed
Length
26km
Volt
132kV
Commissioned
August 2016

Financier
African Development Bank

Contractor
Jyoti Structures Limited
China CAMC Engineering Company Limited

Scope

Construction of a 26km 132kV line from Sotik to Bomet, and substations at Bomet and Sotik.

 

Benefit

Increase electricity access in Bomet County and its surrounding areas as well as provide high voltage power that will transform this area into an attractive location for agro-based and general industries.